A depiction of Hermes 2. (Image: Kairos Power)
The drive to Kairos Power’s reactor demonstration site in Oak Ridge, Tenn., is not only scenic—it’s historic. Nearly 85 years ago, roughly 30,000 construction workers transformed orchards and farmland into a key Manhattan Project site. Depending on your route, you may pass by one of the three gatehouses that were once military checkpoints controlling access to Atomic Energy Commission production facilities.
The full-scale precast concrete structure used for radiation testing at Kairos Power’s Reactor Demonstration Campus in Oak Ridge, Tenn. (Photo: Kairos Power)
Kairos Power has completed shielded radiation performance testing on a full-scale precast concrete structure at the company’s Reactor Demonstration Campus in Oak Ridge, Tenn., involving the use of an iridium-192 source to measure the movement of radiation through the concrete’s walls, joints, and seams. Kairos expects the results to contribute to schedule and cost estimates for its planned commercial power plants.
TRISO fuel pebbles. (Photo: Kairos Power)
A new strategic partnership is providing Kairos Power with the expertise and specialized facilities of Oak Ridge National Laboratory to help accelerate the development of the California-based company’s Hermes. This partnership is the fourth between ORNL and Kairos Power since 2020, and it is focused in part on the manufacture and management of TRISO fuel pebbles for the fluoride salt–cooled, high-temperature demonstration reactor now under construction in Oak Ridge, Tenn.
Hermes under construction in Oak Ridge, Tenn.
Kairos Power has finalized a contract with the Department of Energy to receive high-assay low-enriched uranium (HALEU) from the agency for the company’s Hermes low-power demonstration reactor, currently under construction in Oak Ridge, Tenn.
In partnership with Los Alamos National Laboratory, Kairos intends to use the DOE-provided material to produce HALEU TRISO fuel pebbles for Hermes. The company views the Hermes test reactor and the fuel fabrication program as crucial to the eventual success of its power-producing Hermes 2 demonstration plant, also to be sited in Oak Ridge, and future commercial fluoride salt–cooled high-temperature reactors.
Kairos Power’s fluoride salt–cooled high-temperature Reactor (KP-FHR) uses TRISO fuel embedded in annular graphite pebbles roughly the size of a golf ball. (Photo: Kairos Power)
Kairos Power and BWX Technologies announced today that they will work together to “collaboratively explore” optimizing commercial production of TRISO fuel for Kairos’s planned advanced reactor fleet—beginning with the 50-MWe Hermes 2, slated for operation in 2030—and other potential customers. Their collaboration could include jointly developing a TRISO fuel fabrication facility.
The 3D-printed forms—inside of which concrete is poured—are used to build radiation shielding columns for Kairos Power’s Hermes Low-Power Demonstration Reactor. (Screen capture from ORNL video)
The Department of Energy’s Manufacturing Demonstration Facility (MDF) at Oak Ridge National Laboratory, in partnership with Kairos Power and Barnard Construction, has successfully developed and validated large-scale, 3D-printed polymer composite forms for casting complex concrete structures.
The test took place at Kairos Power’s Oak Ridge, Tenn., campus, where the Hermes Low-Power Demonstration Reactor is currently under construction.
See a video of construction activity here.
The ETU 3.0 reactor vessel was lowered into position using construction cranes and mounted on a support structure attached to the building’s foundation. (Photo: Kairos Power)
A reactor vessel has been installed by Kairos Power for its third Engineering Test Unit (ETU 3.0) at the company’s campus in Oak Ridge, Tenn.
Deep Isolation’s Universal Canister System. (Photo: Deep Isolation)
Nuclear waste disposal technology company Deep Isolation announced it has successfully completed Project PUCK, a government-funded initiative to demonstrate the feasibility and potential commercial readiness of its Universal Canister System (UCS) to manage TRISO spent nuclear fuel.
Drilling begins. (Photo: Kairos Power)
Kairos Power announced this morning that safety-related nuclear construction has begun at the Oak Ridge, Tenn., site where the company is building its Hermes low-power test reactor. Hermes, a scaled demonstration of Kairos Power’s fluoride salt–cooled, high-temperature reactor technology, became the first non–light water reactor to receive a construction permit from the Nuclear Regulatory Commission in December 2023. The company broke ground at the site in July 2024.
This Deimos core configuration shows the fuel, stainless steel, polyethylene, and borated polyethylene positioned for the THETA project. (Photo: DOE)
Los Alamos National Laboratory recently performed a series of customized criticality experiments to obtain data that will support the transportation of HALEU TRISO fuel, the Department of Energy announced April 21.
Participants celebrate Texas A&M’s announcement about hosting SMR units from four nuclear companies. (Photo: Texas A&M)
Texas A&M chancellor John Sharp has announced that the university could soon become a home to small modular reactors from four advanced nuclear companies: Kairos Power, Natura Resources, Terrestrial Energy, and Aalo Atomics.
Concept art for a Hermes plant. (Image: Kairos Power)
The Nuclear Regulatory Commission announced yesterday that it has directed staff to issue construction permits to Kairos Power for the company's proposed Hermes 2 nonpower test reactor facility to be built at the Heritage Center Industrial Park in Oak Ridge, Tenn. The permits authorize Kairos to build a facility with two 35-MWt test reactors that would use molten salt to cool the reactor cores.
Kairos Power leaders, elected officials, and key partners break ground on the Salt Production Facility at the company’s Manufacturing Development Campus in Mesa del Sol, N.M. (Photo: Kairos Power)
Kairos Power broke ground yesterday on a Salt Production Facility at the company’s newly dedicated Manufacturing Development Campus during an event at a sprawling site in Mesa del Sol, N.M., just south of Albuquerque. The new facility will produce the FLiBe (a mixture of lithium fluoride and beryllium fluoride salts) needed to cool the advanced reactors Kairos Power plans to build, starting with its Hermes nonpower demonstration reactor in Oak Ridge, Tenn., and could be operational and producing salt in 2026, according to an October 3 Department of Energy news release.
Workers begin construction at the Hermes site in Oak Ridge, Tenn. (Photo: Kairos Power)
Earlier today, on a site in Oak Ridge, Tenn., that was formerly home to the K-33 Gaseous Diffusion Plant, Kairos Power marked the start of construction on its low-power demonstration reactor. Named Hermes, the 35-MWt test reactor claims status as the first Gen IV reactor to be approved for construction by the Nuclear Regulatory Commission and the first non–light water reactor to be permitted in the United States in more than 50 years.